Golf Course Pump Station

The $750,000 project is fully funded through the Capital Plan and was approved by the membership in December 2022. The replacement and relocation of the Pump Station is a crucial component to the Irrigation System.

We are in the final stages of town permitting process. Once the permits have been received, we will start the site preparation. The installation of the pump station is expected to start in early 2024.

Golf Course Irrigation System

This $3.2M project was approved by the membership in March 2023. To read the brochure detailing this project, click here.

This project is on schedule to start in March 2024 when we will receive material for storage. Installation is expected to start in May 2024. Additional details about hole closures will be communicated with you closer to the start of the project.